After 45 days fabrication, re-inspection, pre-assembly and 20 days shipment, materials reached Dubai on 8th Oct.
At the same time, our engineer and site supervisor came together to the project, taught workers how to assemble every component, it took around 1 month to prepare everything before self climbing formwork lifted to the structure.
Even though we have already tried to avoid possible problem during assembly, we still came across a few application issues on the site. Thanks to our engineer stayed on site all the time, all related issues were solved quickly, every process went smoothly and project ran faster.
Till 20th, December, inner formwork already climbed one time, outer formwork will be lifted in another 2 or 3 days.
Thought it is our customer’s first time to use self-climbing formwork, the project manager started to know this system well during till now. TECON also supplied all the necessary documents including shop drawings and calculation to the consultancy and finally got their approval.
Therefore, it is easy for them to use climbing formwork on their further projects, and the second and third project are actually all under tendering stage with big win odd after the good experience of TECON quality and site service.
If you have any upcoming project need self-climbing formwork, CONTACT US NOW.